Site investigation works for the proposed Cross Bay Link commenced in March 2015, was completed in November 2015, aiming to obtain necessary geological information for the detailed design works
.The works include:
.Land vertical drilling
.Marine vertical and inclined drilling
.Under-water survey
.Field tests and laboratory test
Contract Information as below:
.Contract No. : NE/2014/04
.Title : Site Investigation for Cross Bay Link, Tseung Kwan O
Contractor : Lam Geotechnics Limited
陸上垂直鑽探工程
用於海上鑽探的升降式工作台
用於海上鑽探的升降式工作台
用於海上鑽探的浮動躉船
用於海上鑽探的浮動躉船
詳細設計階段的土地勘測工程已於2015年11月完工。