Erection of precast box girder
Cast-in-situ V-pier at Junk Bay
Erection of V-pier
nstallation of pile-cap shell
Construction of V-pier, installation of precast pile-cap shell, erection of precast V-pier and precast box girder are in progress at Junk Bay. Fabrication of steel and concrete components of the main bridge at off-site yards in the Mainland is in progress. The heaviest and longest precast full span concrete box girder in Hong Kong was installed on V-piers at Junk Bay in August 2020.