2021年 4 月

Erection of V-pier

Erection of double-arch steel bridge

Erection of decoration wall of V-pier

Construction of Electrical and Mechanical (E&M) Plant Room

Double-arch steel bridge was erected on 26 February, marking a key milestone of the CBL project. The remaining prefabricated bridge components will soon be shipped to Hong Kong for erection.