2021年 6 月

The second phase of erecting precast concrete box girders commenced on 7 June 2021.

The crane barge Xin Zhen Fu 7 was used to erect a precast concrete box girder onto the piers. Its lifting capacity is about 5,000 tonnes. It was the first time that Xin Zhen Fu 7 was deployed for Hong Kong infrastructure project.
Together with the one erected on 7 June 2021, a total of 10 precast concrete box girders have been erected, and the remaining 8 precast concrete box girders will soon be delivered to Hong Kong for subsequent erection.